Public Works: 92% of infrastructure works completed in Al-Yarmouk

Minister of Public Works, Dr. Noura Al-Mutairi, directed the follow-up of infrastructure works in the Yarmouk area. Yesterday, Thursday, Engineer Anwar Al-Balushi, Director General of the General Administration of Health Engineering Affairs at the Ministry, conducted a field visit to inspect and monitor these works.
The Ministry of Public Works stated in a press release that the percentage of completion, according to the approved schedule for the infrastructure contract in the Yarmouk area, stands at 72 percent, while the actual executed completion rate has reached 92 percent.
It added that the sewage network and stormwater drainage network have been completed at 100 percent. Additionally, the telephone network has reached 97 percent completion, the street lighting network 98 percent, and all kerbstone and paving works 100 percent.