82%... Completion Rate of "Infrastructure" in Qurtaubah

Anwar Al-Balushi, Director General of the General Administration of Health Engineering Affairs at the Ministry, conducted a field visit yesterday, Thursday, to monitor the implementation of the contract, which was initiated in April 2024 and has a duration of three years.
According to the approved contractual schedule, the progress achieved so far stands at 75.50 percent, while the actual executed progress to date has reached 82 percent. The breakdown of completed works is as follows:
The works are expected to be completed within the contractual timeframe by April 2, 2027.