Local Report: Nationalizing Workforce in Development Projects... How Long Will the Delay Last?

North Kabd Station Exempted from National Workforce Employment Regulations for Direct Contract with Foreign Company
Translated by Alqyas from Al-Jarida — Original source
“The contract is excluded from the scope of the National Workforce Employment Regulations for the project.” This sentence concluded the direct contracting decision for major development projects. The Central Tenders Board’s decision came after reviewing an official letter from the Ministry of Public Works, which requested the exclusion of the contract for the construction, operation, and maintenance of the North Kabd Power Station from the scope of the National Workforce Employment Regulations. This exclusion applies to a direct contract with a foreign company valued at approximately one billion dinars and lasting for ten years.
This exception, explicitly stated in the contract documents and the Board’s decisions, is not an isolated procedural case. Rather, it reopens questions about the reality of nationalizing the workforce in major development projects, and the role such projects play in alleviating pressure on the state’s general budget and in preparing trained cadres.
Since the launch of the first development plans in 2010, it has been repeatedly emphasized that major capital projects should not be reduced to their construction or technical dimensions, but should serve as a means to achieve social and economic objectives, foremost among them creating sustainable employment opportunities for national workers and building local expertise capable of managing and operating these projects in the long term. However, the exclusion of a project as large as the North Kabd Power Station from the National Workforce Employment Regulations reflects a persistent and clear gap between planning texts and implementation reality, as well as a continuation of precedents set by previous projects that included similar exceptions.
A review of successive development plan documents reveals that the file of nationalizing the workforce remained present in all plans, whether through increasing the participation rates of Kuwaitis in the labor market, linking government projects to training and qualification programs, or reducing reliance on expatriate labor in vital sectors. Yet, the practical implementation of these objectives has repeatedly encountered exceptional decisions that allowed major projects to be awarded to foreign companies without obligating them to employ or train national workers at clear percentages, even if those percentages were lower than the generally accepted standards.
The exclusion of the North Kabd Power Station occurs within the context of high development spending that did not necessarily yield a comparable impact on the local labor market. According to final accounts data, actual spending on development plan projects for the fiscal year 2022/2023 did not exceed approximately 56.4 percent of the adjusted appropriation, reflecting delays in the implementation of a large number of projects. This delay, coupled with the exclusion of some projects from localization requirements, effectively reduces employment opportunities linked to public spending twice: once due to slow implementation, and again due to the lack of commitment to employing Kuwaitis during implementation.
The Ministry of Public Works emerges as one of the highest-spending entities within development plans, accounting for the largest share of development plan expenditures in the fiscal year 2023/2024, at 67.5 percent of the total. Despite this financial weight, the participation of national workers in projects under the ministry, particularly in technical and engineering roles associated with direct implementation, remains limited, according to official monitoring reports.
Previous reports from the General Secretariat of the Supreme Council for Planning and Development indicated that government entities faced approximately 674 challenges during the implementation of the 2023/2024 plan. Administrative challenges constituted the largest share, at 41 percent, followed by technical challenges at 30 percent, financial challenges at 14 percent, and legislative challenges at only 5 percent. Overall, these data reflect that the primary obstacle does not lie in the laws themselves, but rather in management and implementation mechanisms, and in the expansion of regulatory exceptions to circumvent complexities, without any clarity regarding alternatives.
However, this approach raises questions about the indirect costs of these exemptions. Major development projects, such as power and water plants and infrastructure, are inherently ideal environments for knowledge transfer and building national capacity. When these projects are managed almost entirely by foreign companies without clear localization commitments, a strategic opportunity is lost to develop local cadres capable of managing these facilities in the future.
Furthermore, a review of projects repeated across multiple development plans reveals that a lack of continuity in implementation has prevented the formation of stable career paths for citizens. Projects that are delayed or executed in fragmented stages do not create a work environment conducive to long-term planning for employment or training, thereby reinforcing reliance on ready-made imported labor at each implementation phase.
In light of these facts, the relationship between development spending and the localization of national labor appears unbalanced. While billions of dinars are allocated to capital projects, some of these projects are exempt from the associated social obligations, transforming them into development projects in name only, but with limited impact on the national labor market.
Final accounts reflect not only the volume of spending but also the nature of the administrative decisions accompanying it. Each exemption from the national labor force employment list practically represents a job opportunity not offered to citizens, technical expertise not transferred, and human capital not built within the local economy.
As the state moves to update its development vision for the coming phase, the file of localizing national labor in development projects remains one of the key issues testing the efficacy of public spending and its ability to achieve balanced economic and social impact. The issue is no longer merely about including the objective in plans, but rather about the extent to which major projects are committed to achieving it on the ground.