The Ministry of Oil organized a virtual panel discussion titled “Importing Liquefied Natural Gas (LNG) to Meet Electricity Plants’ Needs During the Summer Peak Period and the Role of the Zour Facilities in Covering the Rising Demand for Natural Gas in the State of Kuwait.” The session featured presentations by Eng. Abdullah Al-Ajmi, Head of the Gas Operations Team at Kuwait Petroleum Corporation (KPC), and Eng. Salah Bahzad, Head of the Operations Department at KPC, with participation from staff of the Technical Services Affairs Sector and guests from the Ministry of Electricity, Water and Renewable Energy, the Public Authority for Environment, the Organization of Arab Petroleum Exporting Countries (OAPEC), the General Administration of Information Technology, the Kuwait Institute for Scientific Research, the Central Administration of Statistics, and media representatives.
At the outset of the panel, Sheikh Tamadher Al-Khalid, Director of Public Relations and Petroleum Media at the Ministry of Oil, emphasized that the Zour LNG import facilities play a crucial role within the State of Kuwait’s energy supply framework. Their operational capabilities provide the necessary flexibility for supply continuity and support the steady provision of fuel to electricity and water plants, particularly during the summer months when demand surges sharply.
She noted that the significance of the Zour facilities stems from the integration of their operational system, which begins with receiving LNG supplies from global markets and providing strategic storage capacities, proceeds through regasification of the LNG, and culminates in pumping the gas according to consumer network requirements. This integrated approach enhances supply reliability and strengthens the ability to handle the demands of the summer peak season.
She added that the Ministry of Oil is committed to supporting projects and initiatives related to the energy sector that contribute to meeting the country’s needs and keeping pace with development requirements. She pointed out that the Zour facilities serve as a model highlighting the importance of energy infrastructure in linking LNG supplies from global markets with local market needs, thereby serving the requirements of electricity and water plants and supporting the flexibility of the supply system.
Operational System
During the presentation, Eng. Abdullah Al-Ajmi and Eng. Salah Bahzad discussed the role of the Zour LNG import facilities in meeting energy needs during the summer peak. They explained that the facilities operate as a strategic operational system that ensures continuous fuel supply to electricity and water plants and enhances supply flexibility. This is achieved by providing a flexible global source of natural gas, maintaining a strategic reserve that boosts consumer network reliability, regasifying LNG, pumping it according to network requirements, and maintaining operational readiness during the summer peak season through scheduled maintenance activities.
They outlined the operational capacities of the Zour facilities, stating that the complex includes eight LNG storage tanks, each with a capacity of 225,000 cubic meters, bringing the total storage capacity to 1.8 million cubic meters. The annual throughput capacity stands at 22 million tons, with a supply capacity of 3,000 billion British Thermal Units (BTUs). These capabilities enable the Zour facilities to support local supply for up to 12 days without receiving incoming shipments, based on design and maximum operational capacity parameters.
The presentation addressed the complete supply chain “from shipment to grid,” highlighting the Zour facilities for natural gas imports as a vital link between global liquefied natural gas (LNG) supplies and national gas network requirements during peak demand periods. This process begins with the arrival of LNG carriers from global markets, followed by reception via marine jetties and the unloading system. The gas is then stored in high-capacity cryogenic tanks before being regasified through the vaporization process into natural gas, which is subsequently supplied to consumers and power plants. Through this system, the Zour facilities serve as a bridge between global LNG supplies and national gas network requirements when demand levels rise.
“Summer Peak Challenge”
Under the “Summer Peak Challenge” theme, the presentation emphasized that fuel reliability for power and water plants is a cornerstone of preparedness. Summer witnesses a sharp increase in electricity and water demand, underscoring the importance of stable gas supplies in ensuring service continuity.
These requirements are managed through flexibility in receiving global shipments according to market needs, maintaining reserves based on strategic storage capacity capable of absorbing supply fluctuations, and ensuring rapid response by instantly adjusting shipment volumes in line with consumer network requirements.
The monthly gas demand graph for 2025 clearly illustrates the impact of seasonal demand. Demand stood at 1,000 million standard cubic feet per day (MMscf/d) in January, dropped to 959 million in February, then rose to 1,174 million in March, 1,487 million in April, and 1,750 million in May. As summer months arrived, demand increased to 2,020 MMscf/d in June, peaking annually at 2,100 million in July. It then recorded 2,071 million in August and 1,971 million in September, before declining to 1,609 million in October, 1,107 million in November, and 1,090 MMscf/d in December.
Regarding supply management and maintaining operational readiness, the presentation outlined four mechanisms. The first involves shipment planning by coordinating LNG carrier reception with the Kuwait Petroleum Corporation (KPC) according to seasonal demand levels and inventory requirements. Inventory management relies on continuous monitoring with the global operator through round-the-clock operations to enhance facility efficiency.
The system also includes supply management to the consumer network through continuous coordination and daily plan adjustments for rapid response to needs, alongside continuous monitoring, operation, and follow-up around the clock to ensure operational readiness is maintained.
The presentation also highlighted key operational indicators and achievements recorded up to 2026. The Zour facilities received 445 carriers and took delivery of LNG equivalent to 67 million cubic meters, while the volume of gas dispatched reached approximately 1,263,000 million standard cubic feet.
On the environmental and operational achievements front, the facilities recorded a reduction in greenhouse gas (GHG) emissions by approximately 8,000 tons through nitrogen injection, alongside the adoption of the gas re-liquefaction project.
The presentation concluded by emphasizing that the Zour LNG import facilities constitute a key pillar in enhancing the security and resilience of energy supplies in the State of Kuwait, particularly during summer peak demand periods, relying on reliable supply, operational flexibility, and support for the needs of power and water plants.